For the very first time, remote-controlled machines and an underwater welding robot have installed a new tie-in point on a live gas pipeline, without the pipeline being prepared in advance.

These types of operations can save Statoil lots of money in the long run.

The hot tap installation is the first to be carried out in connection with preparations for Åsgard subsea gas compression in the Norwegian Sea, and thus also represents a milestone for the project. The tie-in point was welded on to the Åsgard B production flowline at a water depth of 265 metres.

After ten days on the field, the hot-tap operation team on board the Technip-owned vessel Scandi Arctic could confirm success in the pioneering operation.

“For a subsea engineer, this can be compared with landing on Mars,” says Kjell Edvard Apeland. He is project manager of the remote-controlled hot tap development in Statoil and head of the operation on the Åsgard field.

Simply explained, a remote-controlled hot tap operation consists of a robot welding a T-piece on to the pipe, while gas is flowing through it. When that has been done, a remote-controlled drilling machine will drill holes in the producing pipeline, with no effect on pressure and production.

“When the compressor module and the manifold for Åsgard subsea compression are installed next year, we will connect the pipeline from these to the hot-tap tie-in point,” says Apeland.

The Åsgard subsea compression project will be realised in 2015, as the first of its kind in the world. Compressors will be installed on the seabed, instead of on a platform. This will improve recovery from the Mikkel and Midgard reservoirs by around 280 million barrels of oil equivalents.