Routines improved for operation and maintenance

"There'll always be some outstanding maintenance, but we shared the dissatisfaction expressed by the Petroleum Safety Authority Norway (PSA) over its scope,” says Jannicke Nilsson, head of operations North Sea west in Statoil.

More than half the backlog in safety-critical servicing on installations operated by Statoil off Norway has been eliminated over the past year. The organisation is working continuously to get better at operating these facilities safely and effectively.


"There'll always be some outstanding maintenance, but we shared the dissatisfaction expressed by the Petroleum Safety Authority Norway (PSA) over its scope,” says Jannicke Nilsson, head of operations North Sea west.

“We’ve accordingly worked throughout the year to reduce the number of jobs queuing up to be done.”

 

Action

Statoil appointed an action team during the summer after the PSA identified seven non-conformances and two improvement items during audits of the Oseberg field centre and the Brage, Heimdal and Grane platforms.


"The team assessing the maintenance backlog has come up with a number of measures to close the non-conformances and improve the position,” says Nilsson.


Action proposed includes developing better methods for calculating present and future needs for servicing.


Work process related to maintenance and risk management will also be improved, and efforts to reduce the maintenance backlog stepped up.


Statoil has built up a specialist team in the maintenance management area, which works continuously on analyses, improvement work and enhancing expertise in the organisation.


Leaks
Statoil has completed its internal investigation into riser incidents on Visund and Njord, and submitted its response earlier this week to the conditions identified in the PSA’s report.


“The gas leaks on these two fields occurred when the pressure layer in three-layer Coflon risers on the installations was breached,” explains Nilsson.


“Our investigation found that these breaches on 9 and 24 April respectively could not have caused the actual risers to be ripped off, with an escalation into a major accident.”


Statoil and the PSA identify the same immediate and underlying causes of the incidents. These relate primarily to the way the group has organised servicing of flexible risers, a lack of governing documentation and a need for further training.


“In the investigation report and our response to the PSA, we list a number of specific measures which have already been implemented since the incidents,” reports Nilsson.


“We also detail action that we’re considering taking in the rather longer term.


“These measures are based on our own experience from the incidents, the PSA’s findings and the lessons learnt during work on the issue since last winter.”

Related news

Latest news

CLOUD COMPUTING, FISHTALK & AKVA CONNECT - SOLUTIONS & AMBITIONS

In partnership with key customers, 

Students design autonomous containers to disrupt sea freight of aquaculture products

Along with eight other graduates, he has developed SEAtrue, 

DNV GL applies data analytics techniques to reduce downtime

“We’ve seen similar results in several other digitalization initiatives we’ve had lately. 

DNV GL and Siemens lead the way in asset lifecycle management for the oil and gas industry

In collaboration with Siemens, 

Eimskip strengthens its worldwide forwarding services by acquiring the logistics company SHIP-LOG A/S in Denmark

Eimskip has strengthened its position in worldwide logistics services by acquiring 75% of the freight forwarding company SHIP-LOG. 

For Sale Assets from the former BMV LAKSEVÄG YARD in Bergen, Norway!

For Sale Assets from the former BMV LAKSEVÄG YARD in Bergen, Norway! The entire shipbuilding and fabricating facility is closing and more than 500 lots is on sale.

Servogear CPP for Seasight II - Future of the Fjords

We are proud to announce that Servogear has been chosen for the delivery of Servogear...

TechnipFMC Signs Agreement with Pall to Supply Slurry Oil Filtration Systems for Fluid Catalytic Cracking Units

The associated activities will be managed by TechnipFMC Process Technology’s center in Houston,

10 Million kroner for verification funding

The Norwegian Research Council has granted 10 million...