Oil&Gas: Production start-up at Goliat postponed

By agreement with the partners in the Goliat licence, and due to the delay in the delivery of the production platform, Eni Norge has decided to postpone production start-up at the Goliat field until the third quarter of 2014.

When the Plan for development and operation (PDO) was submitted, the estimated start-up of the Goliat field was set to Q4 2013.

Most key project areas are progressing as planned. However, the development of the production platform facility has met challenges and increased complexity. These are mainly associated with technological innovations of the production facility.

Based on agreement in the Goliat licence the scheduled departure from the Hyundai Heavy Industries’ yard is postponed to end 2013/Q1 2014.

The progress of the other main activities for the development of Goliat will be maintained despite the delay of the production facility.

The expected cost increase, due to the postponing of the production start-up, is estimated to ca 2,5 billion NOK as a result of the delay.

Eni Norge has previously informed the Ministry of Petroleum and Energy of an increase of  investment cost of ca 3,7 billion NOK. This is mainly linked to an increase in marked prices, longer delivery time for several equipment packages and increased process for raw materials due to heavy pressure in the supplier industry.

The investment cost for the Goliat development is now estimated to ca 36,7 billion NOK. The original development cost was estimated to 30,5 billion 2012 NOK.

Goliat will be the first oil field to come into production in the Barents Sea. Eni Norge is the operator of the field (65 %) with Statoil as its partner (35 %). According to plan, Goliat will produce 170 million barrels of oil over a period of 15 years.

The Goliat field development is based on large turnkey contracts (EPC) for the supply of subsea production systems, flowlines and risers, production facility, power cable to shore, modification of the power grid in the Hammerfest area and a state of the art offshore production facility, including the use of innovative technologies.

Related news

Latest news

New barge to Målsøval Fiskeoppdrett

Akva Master 320 Classic is a modern feed barge optimized for efficient operations.

Supply chain management survey indicates greater pressure on companies to demonstrate sustainability

Companies are struggling to take efficient action across their supply chains, while facing increased demands from stakeholders.

From stamp to screen: DNV GL issues over 50,000 electronic certificates

Since the launch in mid-October 2017, DNV GL has issued approximately 50,000 certificates, 

THERMO-TRANSIT FURTHER STRENGTHENS THE COMPANYS GROWTH

THERMO-TRANSIT FURTHER STRENGTHENS THE COMPANYS GROWTH BY APPOINTING JESPER HANSEN AS CHAIRMAN AND JAKOB HOLM AS CEO.

New Zealand Navy turns to Vestdavit for hands-on experience

Since 2000, Vestdavit has supplied 14 davits for seven NZ Navy vessels.

DNV GL and AEP Ohio win Energy Award for helping new energy efficient technology in ultra-low temperature freezers reach the market

Stirling ultra-low temperature freezers now ENERGY STAR certified

New 4K Displays Enable Cutting-Edge Multi-Data Fishing Vessel Bridge Solution from Furuno Norway

Newbuild Danish trawler 'Gitte Henning' first to benefit from large-format, ultra high definition bridge display innovation.

New DNV GL class notations aim to improve stern tube bearing performance

In the “Shaft align” class notations and the revised main class requirements for single stern tube bearing installations,

DNV GL provides due diligence to institutional lenders for investment in 659 MW Walney offshore wind project

Through DNV GL’s technical assessment to the group of lenders,