National Power Transmission Grid, Mozambique

The purpose of the project is to reinforce and extend the Mozambican national power transmission grid specifically in Maputo, Gaza, Inhambane, Zambeze and Nampula Provinces.


The project includes:

  • 275kV Transmission Line Ressano Garcia – Macia (143km); including modifications to Ressano Garcia substation and new 275/110 kV Macia substation with 1x250MVA, 275/110/33 kV transformer.
  • 110kV transmission line Lindela – Massinga (110km), modifications to Lindela substation; new 110/33kV Massinga substation with a 16MVA 110/33kV transformer; 33kV line Massinga-Maxixe (70km).
  • Rural electrification in Homoine and Morumbene districts (46km 33kV line and LV network).
  • Extension of Maputo substation – installation of 1x400MVA, 400/275kV  transformer & associated equipment.
  • Reinforcement of 4 substations [(Chimuara 1x16MVA & 1x40MVA),(Quelimane 1x50/50/20MVA), Alto Molocue 1x100/100/33MVA), (Nampula 1x50 MVA)] in North region of Mozambique.
    • Power Supply to Beloluane Industrial Park (2x120MVA transformers & associated equipment, implemented as extension to Maputo substation).

The project was divided into two phases:

  • Phase 1 - Production of Design Report, Technical Specifications and Tender Documents including ESIA; Contract negotiations and award
  • Phase 2 - Construction Supervision and Project Management.

The project is structured in Packages: Main Package, Optional Package 1, Optional Package 2, and Optional Package 3. This allows for a stage activation of subsequent works which in turn allows a performance audit at various level before the next optional package is activated.

Services Rendered:

  • Line route survey and environmental impact assessment
  • Cost Estimates
  • Conceptual design and technical specifications
  • Tender documents, tender evaluation and contract negotiations
  • Design approval
  • Construction supervision and project management
     

Client: Electricidade de Moçambique (EdM)

Year:
 2011-2019

Associated companies:


Related news

Latest news

World's fastest ROV? - Project ROST

Traditionally, all cleaning has been carried out from a workboat,

New regional manager takes the helm in key oil and gas markets for DNV GL

Elaborating on the differences in the energy markets which now lie under his new responsibilities in DNV GL,

DNV GL launches certification framework and recommended practice for Carbon Capture and Storage (CCS)

The recommended practice DNVGL-RP-F104 Design and operation of carbon dioxide pipelines, 

DNV GL launches new JDP to test biodegradable lubricants

The test programme will investigate such aspects as hydrodynamic oil film formation,

ROV contracts in Brazil

The new contracts and contract extensions give 1 630 days of ROV services...

Steinsvik Secures a Contract for its First Concrete Barge

Steinsvik’s well-known steel barge design is now complemented by a new and innovative concrete barge design.

Searching for the best biological solutions

AKVA group’s biologists play a key role to ensure that the company’s technology not only meets fish welfare requirements, but also provides the best possible conditions for the fish.

Elisabeth Maråk Støle appointed managing director of Forskningsselskapet SørVest AS

Elisabeth Maråk Støle will take up her position on 1 April 2018 at the latest.

TIME SCALE

We are building chambers for tomatoes to grow in space. The aim is to give food to astronauts going to Mars.