Financial close of Windpark Spui for group of lenders supported by DNV GL technical risk assessment

The power generated at Windpark Spui,

Dnv Gl AS

Due diligence for Dutch onshore wind farm in the province of South Holland focused on technical risks to have 735 MW wind capacity installed by 2020.

ARNHEM, The Netherlands - 31 May 2018 – DNV GL, the world’s largest resource of independent energy experts and certification body, has successfully completed comprehensive due diligence of the Dutch Windpark Spui, for a group of lenders who are providing the debt financing for the project. 

The power generated at Windpark Spui, which will supply renewable electricity to more than 24,000 households, will be sold to Eneco Group, a Dutch sustainable energy company, under a 16-year power purchase agreement. Eurus Energy, a leading Japanese renewable energy company, acquired the project from YARD, a Dutch-based developer of wind energy projects, and its co-developer prior to financial close.

“We’d like to congratulate all the parties involved on this momentous achievement. At a time of intense focus on the wind industry, the financial close of Windpark Spui is integral to fulfilling the commitment of the province of South Holland to have 735 megawatts (MW) of onshore wind capacity installed by 2020. Our interdisciplinary and cross-border team of technical experts provided the lending consortium with comprehensive technical due diligence ahead of their investment,” said Prajeev Rasiah, Vice President & Regional Manager North Europe, Middle East & Africa at DNV GL.

Windpark Spui, a 21 MW wind farm located in the municipality of Korendijk in South Holland, the Netherlands, will consist of five Enercon E-126 EP4 wind turbines, which will have a hub height of 135 meters, a rotor diameter of 127 meters and a rated power of 4.2 MW.

DNV GL’s team of local and international wind experts delivered the technical due diligence which featured an independent engineering review of the technical details of the project and associated contractors and companies, including appraisal, environmental permits, civil and electrical design as well as the environmental site conditions, energy production assessment, construction and operations contracts and financial model. 


Associated companies:


Related news

Latest news

TechnipFMC named top Petroleum International Contractor by ENR

This accomplishment places us in front of companies such as Petrofac,

The world’s energy demand will peak in 2035 prompting a reshaping of energy investment

The electrification trend is already enveloping the automotive industry.

DNV GL launches revised design standard and new certification guideline for floating wind turbines

The role of offshore wind, including floating offshore wind energy, 

Green Corridor JIP delivers innovative bulk carrier designs for a low emissions future

When the IMO confirmed the 2020 deadline for the 0.5 per cent global sulphur cap in 2016, 

DNV GL launches Operations & Analytics Centre in India to enable 24/7 monitoring for renewable assets globally

The new global monitoring centre is especially significant to independent power providers, 

DNV GL awards AiP to Jiangnan Shipyard for 93K cbm very large ethane carrier design “PANDA E”

The flexible, efficient and environmentally friendly design was developed by Jiangnan Shipyard in cooperation with GTT,

DNV GL starts phase II of project to examine the impact of phase-contamination on oil flow meters

Accurate measurement of the production of oil fields is an important means ...

Important message at the “AKVAculture Day”

We won’t be able to create growth unless we can handle the industry’s challenges.

Visit from the Ministry of Trade Industry and Fisheries

The Ministry visited in order to learn more about the industry.