The Hyme oil field on stream

This week, Statoil and its partners began production from the Hyme oil field in the southern part of the Norwegian Sea. Hyme is the second of Statoil’s 12 so-called fast-track projects.

The Hyme field is build with a subsea template tied in to existing infrastructure on the Njord A platform.

“The field came on stream one month earlier than we assumed in the plan for development and operation (PDO). The project execution period from we decided to use Njord A as a tie-in platform and to first oil is thus slightly more than two years, which we are very pleased with,” says Halfdan Knudsen, head of the “fast-track” portfolio in Development and Production Norway (DPN).

The “fast-track” projects consist of discoveries made close to existing fields. In the longer term the aim is to bring these projects from discovery to first oil within 30 months.

The Hyme field was discovered at Haltenbanken in June 2009, 19 kilometres north-east of the Njord A platform. It is tied in to existing infrastructure on Njord A. Hyme extends the production life of the Njord field from 2015 to 2020. The field development plan includes a production well and a water injection well drilled through a subsea template with four well slots. The installation of five new risers and Njord A modifications to receive Hyme production are also part of the project. The investments total some NOK 4.5 billion.

“This development will revitalise the entire area, open for further expansion and increase the production life of Njord,” Knudsen says.

Due to the high reservoir complexity an unconventional well solution has been chosen for Hyme. It involves the use of a multilateral well for optimal drainage of the reservoir.

Estimated volumes according to Statoil: 30 million barrels of oil equivalent. Mainly oil, and some gas.

Associated companies:


Related news

Latest news

World's fastest ROV? - Project ROST

Traditionally, all cleaning has been carried out from a workboat,

New regional manager takes the helm in key oil and gas markets for DNV GL

Elaborating on the differences in the energy markets which now lie under his new responsibilities in DNV GL,

DNV GL launches certification framework and recommended practice for Carbon Capture and Storage (CCS)

The recommended practice DNVGL-RP-F104 Design and operation of carbon dioxide pipelines, 

DNV GL launches new JDP to test biodegradable lubricants

The test programme will investigate such aspects as hydrodynamic oil film formation,

ROV contracts in Brazil

The new contracts and contract extensions give 1 630 days of ROV services...

Steinsvik Secures a Contract for its First Concrete Barge

Steinsvik’s well-known steel barge design is now complemented by a new and innovative concrete barge design.

Searching for the best biological solutions

AKVA group’s biologists play a key role to ensure that the company’s technology not only meets fish welfare requirements, but also provides the best possible conditions for the fish.

Elisabeth Maråk Støle appointed managing director of Forskningsselskapet SørVest AS

Elisabeth Maråk Støle will take up her position on 1 April 2018 at the latest.

TIME SCALE

We are building chambers for tomatoes to grow in space. The aim is to give food to astronauts going to Mars.