The Hyme oil field on stream

This week, Statoil and its partners began production from the Hyme oil field in the southern part of the Norwegian Sea. Hyme is the second of Statoil’s 12 so-called fast-track projects.

The Hyme field is build with a subsea template tied in to existing infrastructure on the Njord A platform.

“The field came on stream one month earlier than we assumed in the plan for development and operation (PDO). The project execution period from we decided to use Njord A as a tie-in platform and to first oil is thus slightly more than two years, which we are very pleased with,” says Halfdan Knudsen, head of the “fast-track” portfolio in Development and Production Norway (DPN).

The “fast-track” projects consist of discoveries made close to existing fields. In the longer term the aim is to bring these projects from discovery to first oil within 30 months.

The Hyme field was discovered at Haltenbanken in June 2009, 19 kilometres north-east of the Njord A platform. It is tied in to existing infrastructure on Njord A. Hyme extends the production life of the Njord field from 2015 to 2020. The field development plan includes a production well and a water injection well drilled through a subsea template with four well slots. The installation of five new risers and Njord A modifications to receive Hyme production are also part of the project. The investments total some NOK 4.5 billion.

“This development will revitalise the entire area, open for further expansion and increase the production life of Njord,” Knudsen says.

Due to the high reservoir complexity an unconventional well solution has been chosen for Hyme. It involves the use of a multilateral well for optimal drainage of the reservoir.

Estimated volumes according to Statoil: 30 million barrels of oil equivalent. Mainly oil, and some gas.

Associated companies:


Related news

Latest news

Biggest feed barge delivery ever

At the shipyard in Gdynia Poland, 7 feed barges were recently loaded onboard the vessel Jumbo Vision. The barges are destined for Canada and will be operational this summer. 

Max Planck and CMR cooperation

Scientists at Christian Michelsen Research are currently developing, together with colleagues from the Max Planck Institute for Iron Research (Germany), the Field Kelvin Probe (FKP). This FKP will enable contactless detect...

Consilium equips 48 buildings in Galway, Ireland, with lifesaving panels

Consilium Building Safety has received a strategical order from our Irish distributor...

CADCAM options for the open-minded

“Naval architects log into the Vestdavit digital library and can download exactly what they need within a couple of minutes,

DNV GL COMPIT Award 2017 for smart underwater robotics

Marco Bibuli was announced as the winner of the DNV GL COMPIT Award 2017, which took place in Cardiff this year. The Italian maritime robotics expert, working at the Italian research centre CNR-ISSIA in Genova, was honoure...

Record Number Applications for the Innovation Award!

A total of 28 applications for the Nor-Fishing Foundation Innovation Award, – which includes a check for NOK 100 000 – has been received by the deadline the 1st of May. This represents a 36% increase from record year ...

Midt-Norsk Havbruk and Plastsveis enter into agreement to build smolt facility

“We have followed the development of technology for smolt production carefully for several years,

DNV GL launches on-demand, web-based forecasting at WindPower 2017

Energy traders and plant operators gain online access to hourly forecast data at plant and regional level...

International Quality Awards announced

The Chartered Quality Institute (CQI) launches a series of quality awards designed to recognize the contribution of quality professionals across the globe.