NPD report reveals causes of cost overruns for field developments on the Norwegian shelf

The Norwegian Petroleum Directorate (NPD), on assignment from the Ministry of Petroleum and Energy (MPE) has reviewed five field developments on the Norwegian shelf to uncover why some developments finish in line with their estimated cost target, while others are much more expensive than planned.

The report deals with field developments in excess of NOK 10 billion, with plans for development and operation approved during the period 2006 – 2008. The specific fields involved are Skarv, *Yme, Valhall redevelopment, Tyrihans and Gjøa.

Most projects on the Norwegian shelf end up with development costs within the range of uncertainty stated in the plan for development and operation (PDO) (+/- 20%), but there are some projects with very extensive overruns.

The NPD’s report reviews both projects with major overruns, and projects that have been carried out on schedule and with costs within the range of uncertainty.

The report also shows that overruns are not a Norwegian phenomenon. Several studies reveal the same trend internationally.

The NPD’s work uncovered four main factors in project implementation that are important for the project’s success:

  • Meticulous work in the engineering phase, that is, in the early phase. This will form the basis for decisions and the ongoing work in the project
  • A clear contract strategy which takes the project’s most important risk elements into account, such as use of new technology and major equipment components
  • Thorough prequalification of the suppliers who contribute to the project
  • Good operator follow-up of the project. This is crucial, regardless of where in the world the construction takes place

All of the projects reviewed by the NPD were built during a period when the market was tight. The high level of activity is a contributing factor to the cost overruns, however, the most important causes lie in the planning, contract strategy, supplier follow-up and project follow-up.

Yme, Valhall redevelopment and Skarv have the largest cost overruns. Gjøa and Tyrihans were completed on time and within the estimated cost range presented in the PDO.

The objective of this work has been to extract lessons learned from the findings, both for the industry and for the authorities.

“We believe that the experience gained from these projects can be transferred to other projects. It is therefore important that the industry studies the findings in our report,” says director Arne Holhjem in the NPD.

“It is important to clarify the responsibilities in a field development. The licensees are responsible for implementing the project within the framework outlined in the PDO. This is a basic principal for our follow-up of the projects.”

“Now we in the NPD have to work through these findings to see how this will impact our follow-up efforts in connection with field developments,” says Arne Holhjem.

*The Yme project was included even though the original investment estimate was less than NOK 10 billion, because the final investments ended up being higher than NOK 10 billion. Tyrihans is included because the development was approved by the Storting (Parliament) in late 2005.


Contact in the Norwegian Petroleum Directorate
Eldbjørg Vaage Melberg, tel.+ 47 51 87 61 00

 

Related news

Latest news

Industry's preferred pipeline standard gets update by DNV GL

A number of requirements related to linepipe fabrication,

Servogear Hybrid CPP for the World’s First Hybrid Catamarans in Commercial Traffic

Norled AS is one of Norway’s largest ferry and express boat operators. 

CMR is helping companies in Hordaland with research-based innovation

CMR has won a contract with Hordaland county council as competence broker. The contract is part of the Research-based Regional Innovation (FORREGION) scheme.

ISO to release final draft of ISO 45001 – Occupational Health & Safety

The ISO 45001 Final Draft International Standard (FDIS) is scheduled to be released for review on November 30. In case of a positive vote the standard is expected to be published in February 2018.

DNV GL helps reduce cost of compliance with innovative approach to independent verification of oil and gas assets

Verification surveys applying remote witnessing involve equipping a technician onsite with hardware (a camera or smartphone) and dedicated software which enable remote...

Renewables exports are increasing, but more rapid growth is required

Reorientation among oil and gas suppliers boosted international sales of renewable energy equipment and services by Norwegian companies, writes Ivar Slengesol, Director of Industry and Clean Technologies at Export Credit N...

The world’s most modern wellboat

The wellboat Ronia Diamond was characterised as the “most modern wellboat the world has seen” during her christening in Bergen on 23 September.

Joint industry collaboration to boost offshore and marine sector with Additive Manufacturing (3D printing), Drone and Digital Twin technologies

DNV GL, A*STAR’s Singapore Institute of Manufacturing Technology (SIMTech) and National Additive Manufacturing Innovation Cluster (NAMIC) ...

DNV GL line optimization brings ten per cent fuel savings for Hapag-Lloyd Cruises’ new expedition cruise vessels

“The design concept for the two new ships was ‘inspired by nature’,” says Dr. Henning Brauer,